Approvals for a new multifamily building in Pennsylvania
This is the list ShovelCue builds for a new multifamily building in Pennsylvania before it knows anything else about the site. It has 136 items in 7 groups.
Required the rules say soLikely usual for this kind of projectCheck locally depends on the site or the town
Due Diligence & Studies
Boundary / ALTA Survey
RequiredFixes the property lines and title exceptions that lenders, boards and designers work from.
Topographic Survey
LikelyGives the grades and elevations the civil and site design are drawn on.
Existing Conditions Survey
LikelyRecords what is on the site today so the design starts from facts.
Utility Survey
LikelyFinds the utility lines on and near the site from mark outs and records.
Geotechnical Investigation / Report
RequiredSoil borings and lab tests that tell the engineers how to design the foundations.
Phase I Environmental Site Assessment
RequiredChecks the site history for contamination. Lenders usually require it before closing.
Phase II Environmental Investigation
Check locallyOnly if the Phase I warrants it.
Wetlands Delineation
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Flood / Floodplain Study
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Traffic Study
LikelyShows the board the traffic the project adds. Counts can depend on the season.
Parking Study
Check locallyOnly if the jurisdiction or program asks for it. Parking approach not provided.
Stormwater / Drainage Study
LikelyShows how the site handles rain under the state and town stormwater rules.
Utility Capacity Study
Check locallyOnly if the jurisdiction or program asks for it.
Environmental Impact Study
Check locallyOnly if the jurisdiction or program asks for it.
Noise Study
Check locallyOnly if the jurisdiction or program asks for it.
Other Project-Specific Study
Check locallyOnly if the jurisdiction or program asks for it.
Land Use & Entitlements
Zoning Verification / Zoning Determination
RequiredA letter from the zoning officer confirming what the zoning allows on this site.
Land Development Plan Approval
LikelyUsual for a new building.
- Agency
- Municipal planning commission and governing body
- State rule
- The town reviews the land development plan and must decide within 90 days of its first meeting after filing.
- Clock
- Set by law
- Source
- legis.state.pa.us
County Planning Commission Review
Check locallyDepends on how the project is approved. Check locally.
- Agency
- County planning commission
- State rule
- The county planning commission reviews the plan, and the town waits for its report or 30 days.
- Clock
- Set by law
- Source
- legis.state.pa.us
Subdivision Approval
Check locallyThe town decides whether this applies. Ask the zoning office.
- Agency
- Municipal planning commission and governing body
- State rule
- The town decides on a subdivision plan within 90 days of its first meeting after filing.
- Clock
- Set by law
- Source
- legis.state.pa.us
Lot Consolidation
Check locallyUsual when a project sits on more than one lot.
Variance (Zoning Hearing Board)
Check locallyThe zoning hearing board opens its hearing within 60 days and decides within 45 days after the last hearing.
- Agency
- Zoning hearing board
- Clock
- Set by law
- Source
- legis.state.pa.us
Conditional Use / Special Exception Approval
Check locallyThe board opens its hearing within 60 days and decides within 45 days after the last hearing.
- Agency
- Governing body or zoning hearing board
- Clock
- Set by law
- Source
- legis.state.pa.us
Public Hearing
LikelyUsual for a new building.
Resolution of Approval
LikelyUsual for a new building.
Appeal Period
LikelyUsual for a new building.
- Agency
- County court of common pleas
- State rule
- Anyone can appeal a land use decision to the county court within 30 days of its entry.
- Clock
- Set by law
- Source
- legis.state.pa.us
Final Plan Recording
LikelyUsual for a new building.
- Agency
- County recorder of deeds
- State rule
- Record the approved final plan with the county recorder of deeds within 90 days of final approval.
- Source
- legis.state.pa.us
Redevelopment Approval
Check locallyDepends on how the project is approved. Check locally. Redevelopment designation not confirmed.
Historic Preservation Approval
Check locallyDepends on how the project is approved. Check locally.
Housing / Oversight Agency Approval
Check locallyDepends on how the project is approved. Check locally.
Improvements Agreement and Financial Security
Check locallyDepends on how the project is approved. Check locally. Redevelopment designation not confirmed.
- Agency
- Municipal governing body
- State rule
- The town holds financial security equal to 110 percent of the cost of required improvements before it signs the final plan.
- Source
- legis.state.pa.us
Off-Site / Off-Tract Improvement Agreement
Check locallyDepends on how the project is approved. Check locally.
Easement Agreement
Check locallyDepends on how the project is approved. Check locally.
Access Agreement
Check locallyDepends on how the project is approved. Check locally.
Other Land Use Approval
Check locallyDepends on how the project is approved. Check locally.
Design & Permit Documents
Civil Design Package
RequiredThe site plan drawings submitted to the board.
Architectural Design Package
RequiredThe building drawings, from schematic design through the board submission.
Structural Design Package
RequiredThe structural drawings the building permit is reviewed on.
Mechanical Design Package
RequiredThe heating, cooling and ventilation drawings for the permit.
Electrical Design Package
RequiredThe electrical drawings for the permit and the utility load request.
Plumbing Design Package
RequiredThe plumbing drawings for the permit.
Fire Protection Design Package
RequiredThe sprinkler and fire protection drawings. The sprinkler design depends on the flow test.
Fire Alarm / Life Safety Design
RequiredThe fire alarm and life safety drawings for the fire code review.
Foundation Design
RequiredThe foundation drawings, designed from the geotechnical report.
Support of Excavation Design
Check locallyUsual when the work disturbs a large part of the site.
Landscape Design
LikelyThe planting and landscape plan, often part of the site plan submission.
Lighting / Photometric Design
Check locallyOnly if the program includes it.
Energy Code Package
RequiredThe energy code report, usually filed with the permit set.
Elevator Design / Coordination
Check locallyStories not provided. Whether elevators are needed depends on the building height.
Low Voltage / Technology Design
Check locallyOnly if the program includes it.
Security / Access Control Design
Check locallyOnly if the program includes it.
Interior Design Package
Check locallyOnly if the program includes it.
Permit Drawing Set
RequiredThe signed and sealed drawing sets the building department reviews.
Issued-for-Construction Drawing Set
LikelyThe final drawings the trades build from, with the permit comments included.
Coordination Drawings
LikelyTrade coordination drawings made after the contracts are awarded.
Environmental & Site Authorizations
Erosion and Sediment Control Plan Approval
Check locallyThe erosion and sediment control plan the county conservation district reviews under the state erosion control rules.
- Agency
- County conservation district
- Source
- pa.gov
NPDES Construction Stormwater Permit
Check locallyUsual when the work disturbs a large part of the site.
- Agency
- Pennsylvania DEP and the county conservation district
- State rule
- An NPDES construction stormwater permit through the county conservation district when you disturb an acre or more.
- Source
- pa.gov
SWPPP Approval
Check locallyUsual when the work disturbs a large part of the site.
Wetlands Permit
Check locallyShovelCue has no Pennsylvania record for this line yet, so check who handles it for this site.
Water Obstruction and Encroachment Permit
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
- Agency
- Pennsylvania DEP
- State rule
- A state water obstruction and encroachment permit for work in or along a stream, floodway or wetland.
- Source
- pa.gov
Flood Hazard / Floodplain Approval
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Dewatering / Discharge Permit
Check locallyOnly if the site or work triggers it.
Soil Import / Export Approval
Check locallyOnly if the site or work triggers it.
Act 2 Notice of Intent to Remediate
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
- Agency
- Pennsylvania DEP Land Recycling Program
- State rule
- A voluntary cleanup starts with a notice of intent to remediate sent to DEP and the town and published locally.
- Source
- files.dep.state.pa.us
Brownfield / Remediation Approval
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Environmental Agency Approval
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Air / Dust Permit
Check locallyOnly if the site or work triggers it.
Tree Removal Approval
Check locallyUsual when the work disturbs a large part of the site.
Wastewater / Sewer Extension Approval
Check locallyShovelCue has no Pennsylvania record for this line yet, so check who handles it for this site.
Act 2 Final Report Approval
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
- Agency
- Pennsylvania DEP Land Recycling Program
- State rule
- DEP reviews the Act 2 final report within 60 days, or 90 for a site specific cleanup, or it is deemed approved.
- Clock
- Set by law
- Source
- files.dep.state.pa.us
Other Environmental Authorization
Check locallyOnly if the site or work triggers it.
Sewage Facilities Planning Module
Check locallyNew development that adds sewage flow usually needs a sewage facilities planning approval from the town and the state before the permit.
- Agency
- Pennsylvania DEP and the municipality
- Clock
- Set by law
- Source
- pacodeandbulletin.gov
PNDI Environmental Review Receipt
LikelyA rare species screening receipt that goes with DEP permit applications. It is valid for two years.
- Agency
- PA DCNR, Game Commission, Fish and Boat Commission and U.S. Fish and Wildlife Service
State Historic Preservation Office Review (PA-SHARE)
Check locallyOnly with a state or federal permit or funding. The state historic office answers within 30 days of a complete submittal.
- Agency
- Pennsylvania State Historic Preservation Office (PHMC)
- Clock
- Set by law
- Source
- pa.gov
Utilities & Infrastructure
Water Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Public Water Supply Construction Permit
Check locallyThe water supplier gets a DEP construction permit or a minor amendment before a public water system is built or changed.
- Agency
- Pennsylvania DEP, applied for by the water supplier
- Clock
- Set by law
- Source
- pacodeandbulletin.gov
Sewer Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Electric Service Approval
Check locallyShovelCue has no Pennsylvania record for this line yet, so check who handles it for this site.
Gas Service Approval
Check locallyShovelCue has no Pennsylvania record for this line yet, so check who handles it for this site.
Fire Flow / Water Capacity Confirmation
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Utility Will-Serve Confirmation
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Utility Authority Approval
Check locallyShovelCue has no Pennsylvania record for this line yet, so check who handles it for this site.
Utility Load Approval
Check locallyShovelCue has no Pennsylvania record for this line yet, so check who handles it for this site.
Utility Design Approval
Check locallyShovelCue has no Pennsylvania record for this line yet, so check who handles it for this site.
Utility Relocation Approval
Check locallyOnly with work in or access from public infrastructure.
Utility Easement Approval
Check locallyOnly with work in or access from public infrastructure.
PennDOT Highway Occupancy Permit
Check locallyA PennDOT highway occupancy permit for a driveway or other work on a state road.
- Agency
- PennDOT
- Source
- pa.gov
County / Regional Road Approval
Check locallyOnly with work in or access from public infrastructure.
Road Opening Permit
Check locallyOnly with work in or access from public infrastructure.
Off-Site Improvement Approval
Check locallyOnly with work in or access from public infrastructure.
Telecom / Fiber Service Approval
LikelyPhone, internet and fiber service to the building.
Railroad / Transit Approval
Check locallyOnly with work in or access from public infrastructure.
Other Infrastructure Agency Approval
Check locallyOnly with work in or access from public infrastructure.
Permits & Construction Authorizations
Demolition Permit
Check locallyUsual when an existing structure is demolished.
Early Work Permit
Check locallyUsual when an existing structure is demolished.
Site Clearing Permit
Check locallyUsual when the work disturbs a large part of the site.
Excavation Permit
Check locallyUsual when the work disturbs a large part of the site.
Foundation Permit
Check locallyUsual when the work disturbs a large part of the site.
Building Permit
RequiredThe town or its third party agency reviews the plans under the Uniform Construction Code and decides within 30 business days.
- Agency
- A municipal building code official or a state certified third party agency
- Clock
- Set by law
- Source
- pacodeandbulletin.gov
Plumbing Permit
RequiredThe plumbing permit, reviewed on the same clock as the building permit.
Electrical Permit
RequiredThe electrical permit, reviewed with the building permit.
Mechanical / HVAC Permit
RequiredThe heating and cooling permit, reviewed with the building permit.
Fire Protection Permit
RequiredThe sprinkler permit, reviewed by the fire code official.
Fire Alarm Permit
RequiredThe fire alarm permit, reviewed by the fire code official.
Elevator Permit
Check locallyStories not provided. Whether elevators are needed depends on the building height.
- Agency
- Pennsylvania Department of Labor and Industry
- State rule
- The state approves the elevator plans and permit and inspects the elevator before use, anywhere in Pennsylvania.
- Source
- pa.gov
Retaining Wall Permit
Check locallyOnly if the scope includes it.
Sign Permit
Check locallyOnly if the scope includes it.
Pool Permit
Check locallyOnly if the scope includes it.
Temporary Structure Permit
Check locallyOnly if the scope includes it.
Temporary Power Permit
LikelyLets the utility connect temporary power for construction.
Fire Department / Fire Marshal Approval
Check locallyOnly if the scope includes it.
Health Department Approval
Check locallyOnly if the scope includes it.
Other Specialty Permit
Check locallyOnly if the scope includes it.
Certificate of Occupancy
RequiredEvery occupiable building needs it before use.
- Agency
- A municipal building code official or a state certified third party agency
- State rule
- The building code official issues the certificate within 5 business days after the final inspection report shows compliance.
- Clock
- Set by law
- Source
- pacodeandbulletin.gov
Construction Readiness
Notice to Proceed / Authorization to Start
LikelyThe owner and lender release to start, with the permit in hand.
Preconstruction Meeting Complete
LikelyThe meeting where the owner, architect and builder agree how the job will run.
Site Logistics Plan Approved
LikelyStaging, haul routes and cranes, reviewed by the owner and the town.
Site Access Established
LikelyThe crews and deliveries can get onto the site.
Parking / Curb Use Approval
LikelyStreet closures or curb use, usually on urban sites.
Temporary Power Available
LikelyPower on site for construction. Utility scheduling drives the date.
Temporary Water Available
LikelyWater on site for construction from a hydrant meter or a temporary tap.
Construction Entrance Installed
LikelyA stabilized entrance so trucks do not track soil onto the road.
Erosion / Sediment Controls Installed
LikelySilt fence and controls in place before digging, as the erosion control plan shows.
PA One Call Notice (811)
LikelyNotify PA One Call at least 3 and no more than 10 business days before any digging or demolition.
- Agency
- Pennsylvania One Call System (811)
- Source
- dli.pa.gov
Site Safety Plan Approved
LikelyThe safety plan for this site, in place before crews start.
Emergency Action Plan Complete
LikelyWhat crews do in an emergency on this site.
Adjacent Property Documentation Complete
LikelyPhotos and a condition survey of neighboring buildings before work starts.
Adjoining Property Access Agreement
LikelyAgreements to work from or protect a neighbor property. Tight lots make these slow.
Construction Fencing / Security Ready
LikelyFencing and security around the site before work starts.
Third-Party Testing Agency Engaged
LikelyThe special inspections agency named on the permit.
Survey Control Established
LikelyThe surveyor sets control points so the building goes in the right place.
Required Site Signage / Postings Complete
LikelyThe permit placard and the labor postings on site.
Temporary Facilities Ready
LikelyTrailers, toilets and other temporary facilities on site.
Crane / Hoist Logistics Approved
LikelyStreet use and pick plans for cranes, plus an FAA filing if the height calls for it.
Major Utility Relocations Complete
LikelyUtility lines in the way are moved before the main work starts.
Site Ready to Mobilize
LikelyThe milestone for your target construction start.
Sources
- legis.state.pa.usLand Development Plan Approval
- pa.govErosion and Sediment Control Plan Approval
- pa.govNPDES Construction Stormwater Permit
- pa.govWater Obstruction and Encroachment Permit
- files.dep.state.pa.usAct 2 Notice of Intent to Remediate
- pacodeandbulletin.govSewage Facilities Planning Module
- conservationexplorer.dcnr.pa.govPNDI Environmental Review Receipt
- pa.govState Historic Preservation Office Review (PA-SHARE)
- pacodeandbulletin.govPublic Water Supply Construction Permit
- pa.govPennDOT Highway Occupancy Permit
- pacodeandbulletin.govBuilding Permit
- pa.govElevator Permit
- dli.pa.govPA One Call Notice (811)
Items with no source link come from the national list and are decided by the town or the site. Ask the local office.