ShovelCue

How long it takes to get a project approved in Tennessee

Most projects in Tennessee start with the town. The town planning board or zoning board must approve the land use, and the town building department issues the building permit.

Below are the five phases of a project in Tennessee, who approves it and how long the path to a building permit usually takes.

Local rules for Nashville, Knoxville and Chattanooga are on file too.

How long to a building permit

These are estimates from typical review times, not promises. They run from due diligence to the building permit, and your town, site and drawings can move them.

A sample list for a new multifamily building in Tennessee

Due Diligence

  • Boundary / ALTA Survey
  • Geotechnical Investigation / Report
  • Phase I Environmental Site Assessment

Entitlements

  • Site Plan Approval
  • Public Hearing
  • Resolution of Approval

Pre-construction

  • Civil Design Package
  • Architectural Design Package
  • Structural Design Package

Construction

Inspections and insurance are tracked here once work starts.

Closeout

  • Certificate of Occupancy

And 60 more for your site.

Get a first look at your project

Get the full list for your project, with the agency, the rule and the source for each item, in your first report.

The five phases in Tennessee

  1. Due DiligenceBefore you commit to a site in Tennessee, you check the survey, the soil, the flood risk and what the zoning allows.
  2. EntitlementsThe town planning board or zoning board must approve the site plan and any zoning relief.
  3. Pre-constructionThe drawings go to the town building department for the building permit and the trade permits, while the state agencies and the utility companies sign off on the parts of the site they control.
  4. ConstructionThe town building department inspects the work in stages with the local fire official, and each stage must pass before it is covered up.
  5. CloseoutThe last inspections lead to the certificate that lets people move in. Then the owner gets the warranties, the manuals and the record drawings.

Who approves a project in Tennessee

Not every project needs all of them.

Questions

How long does it take to get a building permit in Tennessee?

ShovelCue estimates 13 to 18 months for a new multifamily building, from the start of due diligence to the building permit. A retail tenant fit out takes about 5 months, and an addition to a single family home takes 4 to 7 months. Your town and your site can change this.

Who approves a construction project in Tennessee?

Most approvals come from the town, through the town planning board or zoning board, then the town building department. Depending on the site, the state transportation department may also sign off. The utility companies approve new service.

Why is the estimate a range?

Your site and your town decide where in the range you land. In Tennessee the gap is widest for a new multifamily building, about 5 months.

Does a small job in Tennessee need state approvals?

Usually not. A tenant fit out or a small addition is mostly a matter for the town building department. State approvals come in when you build new, disturb ground or work near water or a state road.

How do I see what my own project needs?

Ask for a first look. ShovelCue builds the list for your site and shows the date the project can start.

Get a first look at your project

No account needed for your first report.

This is general information from public sources. It is not legal advice. Confirm every item with your town and the agencies involved before you rely on it.

Other states