Approvals for a new multifamily building in New York
This is the list ShovelCue builds for a new multifamily building in New York before it knows anything else about the site. It has 136 items in 7 groups.
Required the rules say soLikely usual for this kind of projectCheck locally depends on the site or the town
Due Diligence & Studies
Boundary / ALTA Survey
RequiredFixes the property lines and title exceptions that lenders, boards and designers work from.
Topographic Survey
LikelyGives the grades and elevations the civil and site design are drawn on.
Existing Conditions Survey
LikelyRecords what is on the site today so the design starts from facts.
Utility Survey
LikelyFinds the utility lines on and near the site from mark outs and records.
Geotechnical Investigation / Report
RequiredSoil borings and lab tests that tell the engineers how to design the foundations.
Phase I Environmental Site Assessment
RequiredChecks the site history for contamination. Lenders usually require it before closing.
Phase II Environmental Investigation
Check locallyOnly if the Phase I warrants it.
Wetlands Delineation
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Flood / Floodplain Study
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Traffic Study
LikelyShows the board the traffic the project adds. Counts can depend on the season.
Parking Study
Check locallyOnly if the jurisdiction or program asks for it. Parking approach not provided.
Stormwater / Drainage Study
LikelyShows how the site handles rain under the state and town stormwater rules.
Utility Capacity Study
Check locallyOnly if the jurisdiction or program asks for it.
Environmental Impact Study
Check locallyOnly if the jurisdiction or program asks for it.
Noise Study
Check locallyOnly if the jurisdiction or program asks for it.
Other Project-Specific Study
Check locallyOnly if the jurisdiction or program asks for it.
Land Use & Entitlements
Zoning Verification / Zoning Determination
RequiredA letter from the zoning officer confirming what the zoning allows on this site.
Site Plan Approval
LikelyUsual for a new building.
- Agency
- Town planning board or the board the town designates
- State rule
- The board holds a hearing within 62 days of the application and decides within 62 days after the hearing.
- Clock
- Set by law
- Source
- nysenate.gov
County Planning Referral
Check locallyDepends on how the project is approved. Check locally.
- Agency
- County planning board or agency, or regional planning council
- State rule
- The town refers projects near county or state roads or municipal boundaries to the county planning agency, which has 30 days.
- Clock
- Set by law
- Source
- nysenate.gov
Subdivision Approval
Check locallyThe town decides whether this applies. Ask the zoning office.
- Agency
- Town planning board
- State rule
- The board holds a hearing within 62 days of a complete plat and decides within 62 days after the hearing.
- Clock
- Set by law
- Source
- nysenate.gov
Lot Consolidation
Check locallyUsual when a project sits on more than one lot.
Variance (Zoning Board of Appeals)
Check locallyThe zoning board of appeals sets a reasonable hearing date and decides within 62 days after the hearing.
- Agency
- Town zoning board of appeals
- Source
- nysenate.gov
Special Use Permit
Check locallyThe board holds a hearing within 62 days of the application and decides within 62 days after the hearing.
- Agency
- Town planning board or other board the town authorizes
- Clock
- Set by law
- Source
- nysenate.gov
Public Hearing
LikelyUsual for a new building.
Resolution of Approval
LikelyUsual for a new building.
Article 78 Challenge Period
LikelyUsual for a new building.
- Agency
- State Supreme Court
- State rule
- A court challenge to the board's decision must start within 30 days after the decision is filed with the town clerk.
- Clock
- Set by law
- Source
- nysenate.gov
Final Plat Filing with the County Clerk
LikelyUsual for a new building.
- Agency
- County clerk or register
- State rule
- The signed final plat must be filed with the county clerk within 62 days of final approval or the approval expires.
- Clock
- Set by law
- Source
- nysenate.gov
Redevelopment Approval
Check locallyDepends on how the project is approved. Check locally. Redevelopment designation not confirmed.
Historic Preservation Approval
Check locallyDepends on how the project is approved. Check locally.
Housing / Oversight Agency Approval
Check locallyDepends on how the project is approved. Check locally.
Performance Bond or Other Security
Check locallyDepends on how the project is approved. Check locally. Redevelopment designation not confirmed.
- Agency
- Town planning board, with the town board and town attorney
- State rule
- Required improvements are installed before approval, or a performance bond or other security covers their full cost.
- Source
- nysenate.gov
Off-Site / Off-Tract Improvement Agreement
Check locallyDepends on how the project is approved. Check locally.
Easement Agreement
Check locallyDepends on how the project is approved. Check locally.
Access Agreement
Check locallyDepends on how the project is approved. Check locally.
Other Land Use Approval
Check locallyDepends on how the project is approved. Check locally.
SEQR Environmental Review
LikelyNew York requires the reviewing board to decide whether the project may have a significant environmental impact before it approves the plan.
- Agency
- Lead agency under SEQR, usually the planning board
- Clock
- Set by law
- Source
- dec.ny.gov
Design & Permit Documents
Civil Design Package
RequiredThe site plan drawings submitted to the board.
Architectural Design Package
RequiredThe building drawings, from schematic design through the board submission.
Structural Design Package
RequiredThe structural drawings the building permit is reviewed on.
Mechanical Design Package
RequiredThe heating, cooling and ventilation drawings for the permit.
Electrical Design Package
RequiredThe electrical drawings for the permit and the utility load request.
Plumbing Design Package
RequiredThe plumbing drawings for the permit.
Fire Protection Design Package
RequiredThe sprinkler and fire protection drawings. The sprinkler design depends on the flow test.
Fire Alarm / Life Safety Design
RequiredThe fire alarm and life safety drawings for the fire code review.
Foundation Design
RequiredThe foundation drawings, designed from the geotechnical report.
Support of Excavation Design
Check locallyUsual when the work disturbs a large part of the site.
Landscape Design
LikelyThe planting and landscape plan, often part of the site plan submission.
Lighting / Photometric Design
Check locallyOnly if the program includes it.
Energy Code Package
RequiredThe energy code report, usually filed with the permit set.
Elevator Design / Coordination
Check locallyStories not provided. Whether elevators are needed depends on the building height.
Low Voltage / Technology Design
Check locallyOnly if the program includes it.
Security / Access Control Design
Check locallyOnly if the program includes it.
Interior Design Package
Check locallyOnly if the program includes it.
Permit Drawing Set
RequiredThe signed and sealed drawing sets the building department reviews.
Issued-for-Construction Drawing Set
LikelyThe final drawings the trades build from, with the permit comments included.
Coordination Drawings
LikelyTrade coordination drawings made after the contracts are awarded.
Environmental & Site Authorizations
Soil / Erosion Control Approval
Check locallyShovelCue has no New York record for this line yet, so check who handles it for this site.
SPDES General Permit for Construction Activity
Check locallyUsual when the work disturbs a large part of the site.
- Agency
- NYS Department of Environmental Conservation
- State rule
- State construction stormwater permit coverage, filed online before you disturb an acre or more. New York City has lower thresholds.
- Source
- dec.ny.gov
SWPPP Approval
Check locallyUsual when the work disturbs a large part of the site.
State Freshwater or Tidal Wetlands Permit
Check locallyA state permit for work in a regulated wetland or adjacent area. DEC decides 45 or 90 days after a complete application.
- Agency
- NYS Department of Environmental Conservation
- Clock
- Set by law
- Source
- dec.ny.gov
Protection of Waters Permit
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
- Agency
- NYS Department of Environmental Conservation
- State rule
- A state permit to disturb the bed or banks of a protected stream or to excavate or fill in navigable waters.
- Clock
- Set by law
- Source
- dec.ny.gov
Flood Hazard / Floodplain Approval
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Dewatering / Discharge Permit
Check locallyOnly if the site or work triggers it.
Soil Import / Export Approval
Check locallyOnly if the site or work triggers it.
Brownfield Cleanup Program Application and Agreement
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
- Agency
- NYS Department of Environmental Conservation
- State rule
- Entry to the state Brownfield Cleanup Program for a contaminated site, ending in a signed Brownfield Cleanup Agreement.
- Source
- dec.ny.gov
Brownfield / Remediation Approval
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Environmental Agency Approval
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Air / Dust Permit
Check locallyOnly if the site or work triggers it.
Tree Removal Approval
Check locallyUsual when the work disturbs a large part of the site.
Wastewater / Sewer Extension Approval
Check locallyShovelCue has no New York record for this line yet, so check who handles it for this site.
Certificate of Completion (Brownfield Cleanup Program)
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
- Agency
- NYS Department of Environmental Conservation
- State rule
- DEC issues a Certificate of Completion after it approves the Final Engineering Report for the cleanup.
- Source
- dec.ny.gov
Other Environmental Authorization
Check locallyOnly if the site or work triggers it.
State Historic Preservation Office Project Review (CRIS)
Check locallyA state or federal permit or funding brings a historic and archaeological review by the State Historic Preservation Office.
- Agency
- NYS Office of Parks, Recreation and Historic Preservation
- Source
- parks.ny.gov
Natural Heritage Project Screening (Rare Species)
Check locallyA screening for rare plants, animals and natural communities when the site is in or near a mapped area.
- Agency
- New York Natural Heritage Program and NYS Department of Environmental Conservation
- Source
- dec.ny.gov
Utilities & Infrastructure
Water Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Water Main Extension Permit
Check locallyShovelCue has no New York record for this line yet, so check who handles it for this site.
Sewer Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Electric Service Approval
Check locallyShovelCue has no New York record for this line yet, so check who handles it for this site.
Gas Service Approval
Check locallyShovelCue has no New York record for this line yet, so check who handles it for this site.
Fire Flow / Water Capacity Confirmation
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Utility Will-Serve Confirmation
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Utility Authority Approval
Check locallyShovelCue has no New York record for this line yet, so check who handles it for this site.
Utility Load Approval
Check locallyShovelCue has no New York record for this line yet, so check who handles it for this site.
Utility Design Approval
Check locallyShovelCue has no New York record for this line yet, so check who handles it for this site.
Utility Relocation Approval
Check locallyOnly with work in or access from public infrastructure.
Utility Easement Approval
Check locallyOnly with work in or access from public infrastructure.
NYSDOT Highway Work Permit
Check locallyA state highway work permit for a driveway or other work on a state highway the site fronts.
- Agency
- NYS Department of Transportation
- Source
- dot.ny.gov
County / Regional Road Approval
Check locallyOnly with work in or access from public infrastructure.
Road Opening Permit
Check locallyOnly with work in or access from public infrastructure.
Off-Site Improvement Approval
Check locallyOnly with work in or access from public infrastructure.
Telecom / Fiber Service Approval
LikelyPhone, internet and fiber service to the building.
Railroad / Transit Approval
Check locallyOnly with work in or access from public infrastructure.
Other Infrastructure Agency Approval
Check locallyOnly with work in or access from public infrastructure.
Permits & Construction Authorizations
Demolition Permit
Check locallyUsual when an existing structure is demolished.
Early Work Permit
Check locallyUsual when an existing structure is demolished.
Site Clearing Permit
Check locallyUsual when the work disturbs a large part of the site.
Excavation Permit
Check locallyUsual when the work disturbs a large part of the site.
Foundation Permit
Check locallyUsual when the work disturbs a large part of the site.
Building Permit
RequiredThe local code enforcement program issues the building permit under the state Uniform Code and Energy Code.
- Agency
- City, town, village or county code enforcement official
- Source
- dos.ny.gov
Plumbing Permit
RequiredThe plumbing permit, reviewed on the same clock as the building permit.
Electrical Permit
RequiredThe electrical permit, reviewed with the building permit.
Mechanical / HVAC Permit
RequiredThe heating and cooling permit, reviewed with the building permit.
Fire Protection Permit
RequiredThe sprinkler permit, reviewed by the fire code official.
Fire Alarm Permit
RequiredThe fire alarm permit, reviewed by the fire code official.
Elevator Permit
Check locallyStories not provided. Whether elevators are needed depends on the building height.
Retaining Wall Permit
Check locallyOnly if the scope includes it.
Sign Permit
Check locallyOnly if the scope includes it.
Pool Permit
Check locallyOnly if the scope includes it.
Temporary Structure Permit
Check locallyOnly if the scope includes it.
Temporary Power Permit
LikelyLets the utility connect temporary power for construction.
Fire Department / Fire Marshal Approval
Check locallyOnly if the scope includes it.
Health Department Approval
Check locallyOnly if the scope includes it.
Other Specialty Permit
Check locallyOnly if the scope includes it.
Certificate of Occupancy or Certificate of Compliance
RequiredEvery occupiable building needs it before use.
- Agency
- City, town, village or county code enforcement official
- State rule
- A certificate of occupancy or certificate of compliance is required before using any work done under a building permit.
- Source
- dos.ny.gov
Construction Readiness
Notice to Proceed / Authorization to Start
LikelyThe owner and lender release to start, with the permit in hand.
Preconstruction Meeting Complete
LikelyThe meeting where the owner, architect and builder agree how the job will run.
Site Logistics Plan Approved
LikelyStaging, haul routes and cranes, reviewed by the owner and the town.
Site Access Established
LikelyThe crews and deliveries can get onto the site.
Parking / Curb Use Approval
LikelyStreet closures or curb use, usually on urban sites.
Temporary Power Available
LikelyPower on site for construction. Utility scheduling drives the date.
Temporary Water Available
LikelyWater on site for construction from a hydrant meter or a temporary tap.
Construction Entrance Installed
LikelyA stabilized entrance so trucks do not track soil onto the road.
Erosion / Sediment Controls Installed
LikelySilt fence and controls in place before digging, as the erosion control plan shows.
811 Excavation Notice
LikelyNotify the one call system at least 2 and no more than 10 working days before excavation or demolition.
- Agency
- New York one call notification system (811)
- Source
- documents.dps.ny.gov
Site Safety Plan Approved
LikelyThe safety plan for this site, in place before crews start.
Emergency Action Plan Complete
LikelyWhat crews do in an emergency on this site.
Adjacent Property Documentation Complete
LikelyPhotos and a condition survey of neighboring buildings before work starts.
Adjoining Property Access Agreement
LikelyAgreements to work from or protect a neighbor property. Tight lots make these slow.
Construction Fencing / Security Ready
LikelyFencing and security around the site before work starts.
Third-Party Testing Agency Engaged
LikelyThe special inspections agency named on the permit.
Survey Control Established
LikelyThe surveyor sets control points so the building goes in the right place.
Required Site Signage / Postings Complete
LikelyThe permit placard and the labor postings on site.
Temporary Facilities Ready
LikelyTrailers, toilets and other temporary facilities on site.
Crane / Hoist Logistics Approved
LikelyStreet use and pick plans for cranes, plus an FAA filing if the height calls for it.
Major Utility Relocations Complete
LikelyUtility lines in the way are moved before the main work starts.
Site Ready to Mobilize
LikelyThe milestone for your target construction start.
Sources
- nysenate.govSite Plan Approval
- nysenate.govCounty Planning Referral
- nysenate.govSubdivision Approval
- nysenate.govVariance (Zoning Board of Appeals)
- nysenate.govSpecial Use Permit
- nysenate.govPerformance Bond or Other Security
- dec.ny.govSEQR Environmental Review
- dec.ny.govSPDES General Permit for Construction Activity
- dec.ny.govState Freshwater or Tidal Wetlands Permit
- dec.ny.govProtection of Waters Permit
- dec.ny.govBrownfield Cleanup Program Application and Agreement
- dec.ny.govCertificate of Completion (Brownfield Cleanup Program)
- parks.ny.govState Historic Preservation Office Project Review (CRIS)
- dec.ny.govNatural Heritage Project Screening (Rare Species)
- dot.ny.govNYSDOT Highway Work Permit
- dos.ny.govBuilding Permit
- documents.dps.ny.gov811 Excavation Notice
Items with no source link come from the national list and are decided by the town or the site. Ask the local office.