Approvals for a new single family home in New York
This is the list ShovelCue builds for a new single family home in New York before it knows anything else about the site. It has 39 items in 7 groups.
Required the rules say soLikely usual for this kind of projectCheck locally depends on the site or the town
Due Diligence & Studies
Boundary / ALTA Survey
RequiredA boundary survey fixes the lot lines the building is placed from.
Topographic Survey
LikelyGives the grades the house, driveway and drainage are drawn on.
Geotechnical Investigation / Report
Check locallyOnly where the soils, a slope or the building department call for borings.
Wetlands Delineation
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Flood / Floodplain Study
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Stormwater / Drainage Study
Check locallySome towns ask for a drainage plan for a new building.
Land Use & Entitlements
Variance (Zoning Board of Appeals)
Check locallyThe zoning board of appeals sets a reasonable hearing date and decides within 62 days after the hearing.
- Agency
- Town zoning board of appeals
- Source
- nysenate.gov
Historic Preservation Approval
Check locallyOnly in a historic district, where the commission reviews new buildings.
Zoning Permit
RequiredThe zoning office confirms the new building meets the setbacks, height and lot coverage.
HOA or Architectural Review Approval
Check locallyAn HOA may need to approve the house design before it is built.
Design & Permit Documents
Civil Design Package
Check locallyMany towns ask for a lot grading and utility plan for a new building.
Architectural Design Package
RequiredThe building drawings, from design through the permit set.
Structural Design Package
LikelyThe structural drawings the building permit is reviewed on.
Fire Protection Design Package
Check locallyOnly where the building code or the town requires sprinklers.
Foundation Design
LikelyThe foundation design for the new building.
Energy Code Package
RequiredThe energy code report, usually filed with the permit set.
Permit Drawing Set
RequiredThe signed and sealed drawing sets the building department reviews.
Issued-for-Construction Drawing Set
LikelyThe final drawings the trades build from, with the permit comments included.
Environmental & Site Authorizations
Soil / Erosion Control Approval
Check locallyShovelCue has no New York record for this line yet, so check who handles it for this site.
Utilities & Infrastructure
Water Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Sewer Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Electric Service Approval
Check locallyShovelCue has no New York record for this line yet, so check who handles it for this site.
Road Opening Permit
LikelyA new driveway or utility connection in the street needs a road opening permit.
Permits & Construction Authorizations
Demolition Permit
Check locallyUsual when an existing structure is demolished.
Building Permit
RequiredThe local code enforcement program issues the building permit under the state Uniform Code and Energy Code.
- Agency
- City, town, village or county code enforcement official
- Source
- dos.ny.gov
Plumbing Permit
RequiredThe plumbing permit, reviewed on the same clock as the building permit.
Electrical Permit
RequiredThe electrical permit, reviewed with the building permit.
Mechanical / HVAC Permit
RequiredThe heating and cooling permit, reviewed with the building permit.
Fire Protection Permit
Check locallyOnly where the building code or the town requires sprinklers.
Retaining Wall Permit
Check locallyOnly if the scope includes it.
Temporary Power Permit
LikelyLets the utility connect temporary power for construction.
Health Department Approval
Check locallyOnly with a well or septic system, or food service.
Certificate of Occupancy or Certificate of Compliance
RequiredEvery occupiable building needs it before use.
- Agency
- City, town, village or county code enforcement official
- State rule
- A certificate of occupancy or certificate of compliance is required before using any work done under a building permit.
- Source
- dos.ny.gov
Construction Readiness
Construction Entrance Installed
LikelyA stabilized entrance so trucks do not track soil onto the road.
Erosion / Sediment Controls Installed
LikelySilt fence and controls in place before digging, as the erosion control plan shows.
811 Excavation Notice
LikelyNotify the one call system at least 2 and no more than 10 working days before excavation or demolition.
- Agency
- New York one call notification system (811)
- Source
- documents.dps.ny.gov
Survey Control Established
LikelyThe surveyor sets control points so the building goes in the right place.
Required Site Signage / Postings Complete
LikelyThe permit placard and the labor postings on site.
Site Ready to Mobilize
LikelyThe milestone for your target construction start.
Sources
- nysenate.govVariance (Zoning Board of Appeals)
- dos.ny.govBuilding Permit
- documents.dps.ny.gov811 Excavation Notice
Items with no source link come from the national list and are decided by the town or the site. Ask the local office.