Approvals for a new multifamily building in Connecticut
This is the list ShovelCue builds for a new multifamily building in Connecticut before it knows anything else about the site. It has 139 items in 7 groups.
Required the rules say soLikely usual for this kind of projectCheck locally depends on the site or the town
Due Diligence & Studies
Boundary / ALTA Survey
RequiredFixes the property lines and title exceptions that lenders, boards and designers work from.
Topographic Survey
LikelyGives the grades and elevations the civil and site design are drawn on.
Existing Conditions Survey
LikelyRecords what is on the site today so the design starts from facts.
Utility Survey
LikelyFinds the utility lines on and near the site from mark outs and records.
Geotechnical Investigation / Report
RequiredSoil borings and lab tests that tell the engineers how to design the foundations.
Phase I Environmental Site Assessment
RequiredChecks the site history for contamination. Lenders usually require it before closing.
Phase II Environmental Investigation
Check locallyOnly if the Phase I warrants it.
Wetlands Delineation
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Flood / Floodplain Study
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Traffic Study
LikelyShows the board the traffic the project adds. Counts can depend on the season.
Parking Study
Check locallyOnly if the jurisdiction or program asks for it. Parking approach not provided.
Stormwater / Drainage Study
LikelyShows how the site handles rain under the state and town stormwater rules.
Utility Capacity Study
Check locallyOnly if the jurisdiction or program asks for it.
Environmental Impact Study
Check locallyOnly if the jurisdiction or program asks for it.
Noise Study
Check locallyOnly if the jurisdiction or program asks for it.
Other Project-Specific Study
Check locallyOnly if the jurisdiction or program asks for it.
Land Use & Entitlements
Zoning Verification / Zoning Determination
RequiredA letter from the zoning officer confirming what the zoning allows on this site.
Site Plan Approval
LikelyUsual for a new building.
- Agency
- Zoning commission or planning and zoning commission
- State rule
- The commission decides within 65 days of receipt. If it does not deny or modify the plan in time, approval is presumed.
- Clock
- Set by law
- Source
- cga.ct.gov
County / Regional Planning Approval
Check locallyDepends on how the project is approved. Check locally.
Subdivision Approval
Check locallyThe town decides whether this applies. Ask the zoning office.
- Agency
- Planning commission or planning and zoning commission
- State rule
- With no hearing the commission decides within 65 days of receipt. With a hearing the 65, 35 and 65 day steps apply.
- Clock
- Set by law
- Source
- cga.ct.gov
Lot Consolidation
Check locallyUsual when a project sits on more than one lot.
Variance (Zoning Board of Appeals)
Check locallyThe hearing starts within 65 days of the application and the board decides within 65 days after it ends.
- Agency
- Zoning Board of Appeals
- Clock
- Set by law
- Source
- cga.ct.gov
Special Permit or Special Exception
Check locallyThe hearing starts within 65 days of the application and the board decides within 65 days after it ends.
- Agency
- Zoning or Planning and Zoning Commission
- Clock
- Set by law
- Source
- cga.ct.gov
Public Hearing
LikelyUsual for a new building.
- Agency
- The commission or board hearing the application
- State rule
- Newspaper notice runs twice, the first 10 to 15 days before the hearing and the last at least two days before.
- Clock
- Set by law
- Source
- cga.ct.gov
Notice of Decision Published
LikelyUsual for a new building.
- Agency
- The deciding commission or board
- State rule
- Notice of the decision is published in a newspaper and mailed to the applicant within 15 days after the decision.
- Clock
- Set by law
- Source
- cga.ct.gov
Zoning Appeal Period (15 Days)
LikelyUsual for a new building.
- Agency
- Superior Court for the judicial district where the town is
- State rule
- An appeal must be served within 15 days from the date the notice of the decision was published.
- Clock
- Set by law
- Source
- cga.ct.gov
Decision Recorded in the Town Land Records
LikelyUsual for a new building.
- Agency
- Town clerk, in the town land records
- State rule
- A variance, special permit or special exception is not effective until a certified copy is recorded in the town land records.
- Source
- cga.ct.gov
Redevelopment Approval
Check locallyDepends on how the project is approved. Check locally. Redevelopment designation not confirmed.
Historic District Certificate of Appropriateness
Check locallyDepends on how the project is approved. Check locally.
- Agency
- Local historic district commission
- State rule
- Only in a local historic district. The commission holds a hearing and decides within 65 days or the certificate is approved.
- Clock
- Set by law
- Source
- cga.ct.gov
Affordable Housing Application (Section 8-30g)
Check locallyDepends on how the project is approved. Check locally.
- Agency
- Zoning or planning commission, then the Superior Court on appeal
- State rule
- Housing with 30 percent deed restricted homes can appeal a denial, and the commission must prove its reasons in court.
- Source
- cga.ct.gov
Developer / Development Agreement
Check locallyDepends on how the project is approved. Check locally. Redevelopment designation not confirmed.
Off-Site / Off-Tract Improvement Agreement
Check locallyDepends on how the project is approved. Check locally.
Easement Agreement
Check locallyDepends on how the project is approved. Check locally.
Access Agreement
Check locallyDepends on how the project is approved. Check locally.
Other Land Use Approval
Check locallyDepends on how the project is approved. Check locally.
Coastal Site Plan Review
Check locallyOnly inside the coastal boundary of a shoreline town. The same town board reviews it with the zoning or subdivision application.
- Agency
- The town commission or board deciding the underlying application
- Source
- portal.ct.gov
Design & Permit Documents
Civil Design Package
RequiredThe site plan drawings submitted to the board.
Architectural Design Package
RequiredThe building drawings, from schematic design through the board submission.
Structural Design Package
RequiredThe structural drawings the building permit is reviewed on.
Mechanical Design Package
RequiredThe heating, cooling and ventilation drawings for the permit.
Electrical Design Package
RequiredThe electrical drawings for the permit and the utility load request.
Plumbing Design Package
RequiredThe plumbing drawings for the permit.
Fire Protection Design Package
RequiredThe sprinkler and fire protection drawings. The sprinkler design depends on the flow test.
Fire Alarm / Life Safety Design
RequiredThe fire alarm and life safety drawings for the fire code review.
Foundation Design
RequiredThe foundation drawings, designed from the geotechnical report.
Support of Excavation Design
Check locallyUsual when the work disturbs a large part of the site.
Landscape Design
LikelyThe planting and landscape plan, often part of the site plan submission.
Lighting / Photometric Design
Check locallyOnly if the program includes it.
Energy Code Package (2021 IECC with Connecticut Amendments)
RequiredThe 2022 State Building Code adopts the 2021 International Energy Conservation Code with state amendments. Air leakage testing is required.
- Agency
- Local building official
- Source
- portal.ct.gov
Elevator Design / Coordination
Check locallyStories not provided. Whether elevators are needed depends on the building height.
Low Voltage / Technology Design
Check locallyOnly if the program includes it.
Security / Access Control Design
Check locallyOnly if the program includes it.
Interior Design Package
Check locallyOnly if the program includes it.
Permit Drawing Set
RequiredThe signed and sealed drawing sets the building department reviews.
Issued-for-Construction Drawing Set
LikelyThe final drawings the trades build from, with the permit comments included.
Coordination Drawings
LikelyTrade coordination drawings made after the contracts are awarded.
Environmental & Site Authorizations
Erosion and Sediment Control Plan Approval
Check locallyThe town commission reviews the erosion and sediment control plan. Under five acres its approval also covers the state stormwater permit.
- Agency
- Town planning and zoning, inland wetlands or conservation commission
- Source
- portal.ct.gov
DEEP Construction Stormwater General Permit
Check locallyUsual when the work disturbs a large part of the site.
- Agency
- Connecticut DEEP
- State rule
- Five acres or more applies to DEEP, which takes 60 or 90 days. Under five acres the town approval covers it.
- Clock
- Set by law
- Source
- portal.ct.gov
Stormwater Pollution Control Plan
Check locallyUsual when the work disturbs a large part of the site.
- Agency
- Prepared by a qualified professional under the DEEP general permit
- State rule
- For five acres or more a qualified professional prepares the plan, and a qualified professional or the conservation district certifies it.
- Source
- portal.ct.gov
Inland Wetlands Permit
Check locallyThe town wetlands agency acts within 65 days of receipt, or within 35 days after a hearing closes.
- Agency
- Town inland wetlands agency
- Clock
- Set by law
- Source
- cga.ct.gov
DEEP Coastal Permit (Structures, Dredging and Fill or Tidal Wetlands)
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
- Agency
- Connecticut DEEP Land and Water Resources Division
- State rule
- Only for work waterward of the coastal jurisdiction line or in tidal wetlands. DEEP strongly recommends a meeting before applying.
- Source
- portal.ct.gov
Flood Hazard / Floodplain Approval
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Dewatering / Discharge Permit
Check locallyOnly if the site or work triggers it.
Soil Import / Export Approval
Check locallyOnly if the site or work triggers it.
Release Reporting and Cleanup (Release-Based Cleanup Program)
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
- Agency
- Connecticut DEEP Remediation Division
- State rule
- Since March 1, 2026 the Release-Based Cleanup program governs contaminated sites. It replaced the Transfer Act.
- Source
- portal.ct.gov
Brownfield / Remediation Approval
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Asbestos Abatement Notification
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
- Agency
- Connecticut Department of Public Health Asbestos Program
- State rule
- The asbestos abatement notice goes to the Department of Public Health at least 10 days before abatement starts.
- Clock
- Set by law
- Source
- portal.ct.gov
Air / Dust Permit
Check locallyOnly if the site or work triggers it.
Tree Removal Approval
Check locallyUsual when the work disturbs a large part of the site.
Wastewater / Sewer Extension Approval
Check locallyShovelCue has no Connecticut record for this line yet, so check who handles it for this site.
Environmental Closure / No Further Action
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Other Environmental Authorization
Check locallyOnly if the site or work triggers it.
Flood Management Certification
Check locallyOnly when a state agency funds or carries out work in a floodplain. DEEP decides within 90 days of the application.
- Agency
- Connecticut DEEP, on the application of the state agency funding the work
- Clock
- Set by law
- Source
- portal.ct.gov
Water Diversion Permit
Check locallyOnly for withdrawing over 50,000 gallons a day, collecting runoff from over 100 acres, or altering a watercourse.
- Agency
- Connecticut DEEP
- Source
- portal.ct.gov
Natural Diversity Data Base Review
Check locallyOnly when the site is in a mapped state listed species area and the project needs a state permit.
- Agency
- Connecticut DEEP Natural Diversity Data Base
- Source
- portal.ct.gov
State Historic Preservation Office Review
Check locallyOnly when a state or federal agency funds, permits or approves the project. The office usually answers within 30 days.
- Agency
- Connecticut State Historic Preservation Office
- Source
- portal.ct.gov
Utilities & Infrastructure
Water Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Water Main Extension Permit
Check locallyShovelCue has no Connecticut record for this line yet, so check who handles it for this site.
Sewer Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Electric Service Approval
Check locallyThe electric company that serves the town confirms it can serve the site and designs the new service.
- Agency
- Eversource, United Illuminating or the municipal electric utility
- Source
- portal.ct.gov
Gas Service Approval
Check locallyThe gas company that serves the town confirms it can serve the site and designs the new service.
- Agency
- Connecticut Natural Gas, Southern Connecticut Gas or Eversource
- Source
- portal.ct.gov
Fire Flow / Water Capacity Confirmation
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Utility Will-Serve Confirmation
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Utility Authority Approval
Check locallyShovelCue has no Connecticut record for this line yet, so check who handles it for this site.
Utility Load Approval
Check locallyShovelCue has no Connecticut record for this line yet, so check who handles it for this site.
Utility Design Approval
Check locallyShovelCue has no Connecticut record for this line yet, so check who handles it for this site.
Utility Relocation Approval
Check locallyOnly with work in or access from public infrastructure.
Utility Easement Approval
Check locallyOnly with work in or access from public infrastructure.
CTDOT Encroachment Permit
Check locallyA CTDOT encroachment permit for a driveway or work on a state highway.
- Agency
- CTDOT
- Source
- portal.ct.gov
County / Regional Road Approval
Check locallyOnly with work in or access from public infrastructure.
Road Opening Permit
Check locallyOnly with work in or access from public infrastructure.
Off-Site Improvement Approval
Check locallyOnly with work in or access from public infrastructure.
Telecom / Fiber Service Approval
LikelyPhone, internet and fiber service to the building.
Railroad / Transit Approval
Check locallyOnly with work in or access from public infrastructure.
Other Infrastructure Agency Approval
Check locallyOnly with work in or access from public infrastructure.
OSTA Major Traffic Generator Review
Check locallyOnly for 100,000 square feet or more or 200 or more parking spaces. Housing of 100 units or less is exempt.
- Agency
- Office of the State Traffic Administration
- Source
- portal.ct.gov
Permits & Construction Authorizations
Demolition Permit
Check locallyUsual when an existing structure is demolished.
- Agency
- Local building official
- State rule
- The owner and a licensed demolition contractor sign the permit. A town may add a waiting period of up to 180 days.
- Source
- cga.ct.gov
Early Work Permit
Check locallyUsual when an existing structure is demolished.
Site Clearing Permit
Check locallyUsual when the work disturbs a large part of the site.
Excavation Permit
Check locallyUsual when the work disturbs a large part of the site.
Foundation Permit
Check locallyUsual when the work disturbs a large part of the site.
Building Permit
RequiredThe building official must issue or refuse the permit within 30 days after the application is filed.
- Agency
- Local building official
- Clock
- Set by law
- Source
- cga.ct.gov
Plumbing Permit
RequiredThe plumbing permit, reviewed on the same clock as the building permit.
Electrical Permit
RequiredThe local building official issues it under the State Building Code, which adopts the 2020 National Electrical Code.
- Agency
- Local building official
- Source
- portal.ct.gov
Mechanical / HVAC Permit
RequiredThe heating and cooling permit, reviewed with the building permit.
Fire Protection Permit
RequiredThe sprinkler permit, reviewed by the fire code official.
Fire Alarm Permit
RequiredThe fire alarm permit, reviewed by the fire code official.
Elevator Permit
Check locallyStories not provided. Whether elevators are needed depends on the building height.
- Agency
- Connecticut Department of Administrative Services, Office of State Building Inspector
- State rule
- The state approves the elevator plans before installation and inspects the elevator before it may run.
- Source
- portal.ct.gov
Retaining Wall Permit
Check locallyOnly if the scope includes it.
Sign Permit
Check locallyOnly if the scope includes it.
Pool Permit
Check locallyOnly if the scope includes it.
Temporary Structure Permit
Check locallyOnly if the scope includes it.
Temporary Power Permit
LikelyLets the utility connect temporary power for construction.
Local Fire Marshal Plan Review
Check locallyOnly if the scope includes it.
- Agency
- Local fire marshal
- State rule
- The local fire marshal certifies in writing that the plans substantially comply with the State Fire Safety Code before the permit issues.
- Source
- portal.ct.gov
Septic System Approval (Local Director of Health)
Check locallyOnly if the scope includes it.
- Agency
- Local director of health or health district
- State rule
- A site on a septic system needs an approval to construct from the local director of health before the system is built.
- Source
- portal.ct.gov
Other Specialty Permit
Check locallyOnly if the scope includes it.
Certificate of Occupancy
RequiredEvery occupiable building needs it before use.
- Agency
- Local building official
- State rule
- The building official issues it once the zoning officer and the local fire marshal certify the finished building in writing.
- Source
- portal.ct.gov
Construction Readiness
Notice to Proceed / Authorization to Start
LikelyThe owner and lender release to start, with the permit in hand.
Preconstruction Meeting Complete
LikelyThe meeting where the owner, architect and builder agree how the job will run.
Site Logistics Plan Approved
LikelyStaging, haul routes and cranes, reviewed by the owner and the town.
Site Access Established
LikelyThe crews and deliveries can get onto the site.
Parking / Curb Use Approval
LikelyStreet closures or curb use, usually on urban sites.
Temporary Power Available
LikelyPower on site for construction. Utility scheduling drives the date.
Temporary Water Available
LikelyWater on site for construction from a hydrant meter or a temporary tap.
Construction Entrance Installed
LikelyA stabilized entrance so trucks do not track soil onto the road.
Erosion / Sediment Controls Installed
LikelySilt fence and controls in place before digging, as the erosion control plan shows.
Call Before You Dig Notice
LikelyMark the dig area, then notify the clearinghouse at least two full working days before digging. A ticket lasts 30 days.
- Agency
- Call Before You Dig, the state clearinghouse
- Clock
- Set by law
- Source
- eregulations.ct.gov
Site Safety Plan Approved
LikelyThe safety plan for this site, in place before crews start.
Emergency Action Plan Complete
LikelyWhat crews do in an emergency on this site.
Adjacent Property Documentation Complete
LikelyPhotos and a condition survey of neighboring buildings before work starts.
Adjoining Property Access Agreement
LikelyAgreements to work from or protect a neighbor property. Tight lots make these slow.
Construction Fencing / Security Ready
LikelyFencing and security around the site before work starts.
Third-Party Testing Agency Engaged
LikelyThe special inspections agency named on the permit.
Survey Control Established
LikelyThe surveyor sets control points so the building goes in the right place.
Required Site Signage / Postings Complete
LikelyThe permit placard and the labor postings on site.
Temporary Facilities Ready
LikelyTrailers, toilets and other temporary facilities on site.
Crane / Hoist Logistics Approved
LikelyStreet use and pick plans for cranes, plus an FAA filing if the height calls for it.
Major Utility Relocations Complete
LikelyUtility lines in the way are moved before the main work starts.
Site Ready to Mobilize
LikelyThe milestone for your target construction start.
Sources
- cga.ct.govSite Plan Approval
- cga.ct.govHistoric District Certificate of Appropriateness
- cga.ct.govAffordable Housing Application (Section 8-30g)
- portal.ct.govCoastal Site Plan Review
- portal.ct.govEnergy Code Package (2021 IECC with Connecticut Amendments)
- portal.ct.govErosion and Sediment Control Plan Approval
- cga.ct.govInland Wetlands Permit
- portal.ct.govDEEP Coastal Permit (Structures, Dredging and Fill or Tidal Wetlands)
- portal.ct.govRelease Reporting and Cleanup (Release-Based Cleanup Program)
- portal.ct.govAsbestos Abatement Notification
- portal.ct.govFlood Management Certification
- portal.ct.govWater Diversion Permit
- portal.ct.govNatural Diversity Data Base Review
- portal.ct.govState Historic Preservation Office Review
- portal.ct.govElectric Service Approval
- portal.ct.govGas Service Approval
- portal.ct.govCTDOT Encroachment Permit
- portal.ct.govOSTA Major Traffic Generator Review
- cga.ct.govDemolition Permit
- portal.ct.govElevator Permit
- portal.ct.govSeptic System Approval (Local Director of Health)
- eregulations.ct.govCall Before You Dig Notice
Items with no source link come from the national list and are decided by the town or the site. Ask the local office.
Other project types in Connecticut
This is general information from public sources. It is not legal advice. Confirm every item with your town and the agencies named before you rely on it.