Approvals for a new single family home in Connecticut
This is the list ShovelCue builds for a new single family home in Connecticut before it knows anything else about the site. It has 39 items in 7 groups.
Required the rules say soLikely usual for this kind of projectCheck locally depends on the site or the town
Due Diligence & Studies
Boundary / ALTA Survey
RequiredA boundary survey fixes the lot lines the building is placed from.
Topographic Survey
LikelyGives the grades the house, driveway and drainage are drawn on.
Geotechnical Investigation / Report
Check locallyOnly where the soils, a slope or the building department call for borings.
Wetlands Delineation
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Flood / Floodplain Study
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Stormwater / Drainage Study
Check locallySome towns ask for a drainage plan for a new building.
Land Use & Entitlements
Variance (Zoning Board of Appeals)
Check locallyThe hearing starts within 65 days of the application and the board decides within 65 days after it ends.
- Agency
- Zoning Board of Appeals
- Clock
- Set by law
- Source
- cga.ct.gov
Historic District Certificate of Appropriateness
Check locallyOnly in a historic district, where the commission reviews new buildings.
- Agency
- Local historic district commission
- State rule
- Only in a local historic district. The commission holds a hearing and decides within 65 days or the certificate is approved.
- Clock
- Set by law
- Source
- cga.ct.gov
Zoning Permit
RequiredThe zoning office confirms the new building meets the setbacks, height and lot coverage. In Connecticut no building permit issues without the zoning enforcement officer certifying in writing that the work conforms to zoning.
- Agency
- Zoning enforcement officer
- Source
- cga.ct.gov
HOA or Architectural Review Approval
Check locallyAn HOA may need to approve the house design before it is built.
Design & Permit Documents
Civil Design Package
Check locallyMany towns ask for a lot grading and utility plan for a new building.
Architectural Design Package
RequiredThe building drawings, from design through the permit set.
Structural Design Package
LikelyThe structural drawings the building permit is reviewed on.
Fire Protection Design Package
Check locallyOnly where the building code or the town requires sprinklers.
Foundation Design
LikelyThe foundation design for the new building.
Energy Code Package (2021 IECC with Connecticut Amendments)
RequiredThe 2022 State Building Code adopts the 2021 International Energy Conservation Code with state amendments. Air leakage testing is required.
- Agency
- Local building official
- Source
- portal.ct.gov
Permit Drawing Set
RequiredThe signed and sealed drawing sets the building department reviews.
Issued-for-Construction Drawing Set
LikelyThe final drawings the trades build from, with the permit comments included.
Environmental & Site Authorizations
Erosion and Sediment Control Plan Approval
Check locallyThe town commission reviews the erosion and sediment control plan. Under five acres its approval also covers the state stormwater permit.
- Agency
- Town planning and zoning, inland wetlands or conservation commission
- Source
- portal.ct.gov
Utilities & Infrastructure
Water Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Sewer Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Electric Service Approval
Check locallyThe electric company that serves the town confirms it can serve the site and designs the new service.
- Agency
- Eversource, United Illuminating or the municipal electric utility
- Source
- portal.ct.gov
Road Opening Permit
LikelyA new driveway or utility connection in the street needs a road opening permit.
Permits & Construction Authorizations
Demolition Permit
Check locallyUsual when an existing structure is demolished.
- Agency
- Local building official
- State rule
- The owner and a licensed demolition contractor sign the permit. A town may add a waiting period of up to 180 days.
- Source
- cga.ct.gov
Building Permit
RequiredThe building official must issue or refuse the permit within 30 days after the application is filed.
- Agency
- Local building official
- Clock
- Set by law
- Source
- cga.ct.gov
Plumbing Permit
RequiredThe plumbing permit, reviewed on the same clock as the building permit.
Electrical Permit
RequiredThe local building official issues it under the State Building Code, which adopts the 2020 National Electrical Code.
- Agency
- Local building official
- Source
- portal.ct.gov
Mechanical / HVAC Permit
RequiredThe heating and cooling permit, reviewed with the building permit.
Fire Protection Permit
Check locallyOnly where the building code or the town requires sprinklers.
Retaining Wall Permit
Check locallyOnly if the scope includes it.
Temporary Power Permit
LikelyLets the utility connect temporary power for construction.
Septic System Approval (Local Director of Health)
Check locallyOnly with a well or septic system, or food service.
- Agency
- Local director of health or health district
- State rule
- A site on a septic system needs an approval to construct from the local director of health before the system is built.
- Source
- portal.ct.gov
Certificate of Occupancy
RequiredEvery occupiable building needs it before use.
- Agency
- Local building official
- State rule
- The building official issues it once the zoning officer and the local fire marshal certify the finished building in writing.
- Source
- portal.ct.gov
Construction Readiness
Construction Entrance Installed
LikelyA stabilized entrance so trucks do not track soil onto the road.
Erosion / Sediment Controls Installed
LikelySilt fence and controls in place before digging, as the erosion control plan shows.
Call Before You Dig Notice
LikelyMark the dig area, then notify the clearinghouse at least two full working days before digging. A ticket lasts 30 days.
- Agency
- Call Before You Dig, the state clearinghouse
- Clock
- Set by law
- Source
- eregulations.ct.gov
Survey Control Established
LikelyThe surveyor sets control points so the building goes in the right place.
Required Site Signage / Postings Complete
LikelyThe permit placard and the labor postings on site.
Site Ready to Mobilize
LikelyThe milestone for your target construction start.
Sources
- cga.ct.govVariance (Zoning Board of Appeals)
- cga.ct.govHistoric District Certificate of Appropriateness
- portal.ct.govEnergy Code Package (2021 IECC with Connecticut Amendments)
- portal.ct.govErosion and Sediment Control Plan Approval
- portal.ct.govElectric Service Approval
- cga.ct.govDemolition Permit
- portal.ct.govSeptic System Approval (Local Director of Health)
- eregulations.ct.govCall Before You Dig Notice
Items with no source link come from the national list and are decided by the town or the site. Ask the local office.
Other project types in Connecticut
This is general information from public sources. It is not legal advice. Confirm every item with your town and the agencies named before you rely on it.