This is the list ShovelCue builds for a retail tenant fit out in Connecticut before it knows anything else about the site. It has 13 items in 4 groups.
Required the rules say soLikely usual for this kind of projectCheck locally depends on the site or the town
Design & Permit Documents
Energy Code Package (2021 IECC with Connecticut Amendments)
Check locallyNew lighting and equipment may need an energy code report with the permit.
- Agency
- Local building official
- State rule
- The 2022 State Building Code adopts the 2021 International Energy Conservation Code with state amendments. Air leakage testing is required.
- Source
- portal.ct.gov
Permit Drawing Set
RequiredCommercial work needs drawings signed and sealed by a design professional for the permit review.
Permits & Construction Authorizations
Building Permit
RequiredA tenant fit-out needs a building permit for the new layout and systems.
- Agency
- Local building official
- State rule
- The building official must issue or refuse the permit within 30 days after the application is filed.
- Clock
- Set by law
- Source
- cga.ct.gov
Plumbing Permit
LikelyNeeded when restrooms, sinks or piping change.
Electrical Permit
RequiredA fit-out almost always adds or moves circuits and lighting.
- Agency
- Local building official
- State rule
- The local building official issues it under the State Building Code, which adopts the 2020 National Electrical Code.
- Source
- portal.ct.gov
Mechanical / HVAC Permit
LikelyA fit-out usually changes ducts, diffusers or units.
Fire Protection Permit
LikelySprinkler heads usually move with new walls and ceilings.
Fire Alarm Permit
Check locallyOnly when the fire alarm devices change.
Sign Permit
Check locallyOnly when the tenant puts up new signs.
Certificate of Occupancy
LikelyA new tenant usually needs a certificate of occupancy before it opens.
- Agency
- Local building official
- State rule
- The building official issues it once the zoning officer and the local fire marshal certify the finished building in writing.
- Source
- portal.ct.gov
Land Use & Entitlements
Landlord or Condo Board Approval
LikelyThe landlord usually approves the plans before they go to the town.
Zoning Permit
Check locallyMany towns check that the new tenant use is allowed with a zoning permit or certificate of use. In Connecticut no building permit issues without the zoning enforcement officer certifying in writing that the work conforms to zoning.
- Agency
- Zoning enforcement officer
- Source
- cga.ct.gov
Environmental & Site Authorizations
Asbestos Inspection and Notification
LikelyA commercial space is checked for asbestos before renovation. In Connecticut the asbestos abatement notice goes to the Department of Public Health at least 10 days before abatement starts.
- Agency
- Connecticut Department of Public Health Asbestos Program
- Source
- portal.ct.gov
Sources
- portal.ct.govEnergy Code Package (2021 IECC with Connecticut Amendments)
- cga.ct.govBuilding Permit
- cga.ct.govZoning Permit
- portal.ct.govAsbestos Inspection and Notification
Items with no source link come from the national list and are decided by the town or the site. Ask the local office.
Other project types in Connecticut
This is general information from public sources. It is not legal advice. Confirm every item with your town and the agencies named before you rely on it.