Approvals for a new single family home in Massachusetts
This is the list ShovelCue builds for a new single family home in Massachusetts before it knows anything else about the site. It has 39 items in 7 groups.
Required the rules say soLikely usual for this kind of projectCheck locally depends on the site or the town
Due Diligence & Studies
Boundary / ALTA Survey
RequiredA boundary survey fixes the lot lines the building is placed from.
Topographic Survey
LikelyGives the grades the house, driveway and drainage are drawn on.
Geotechnical Investigation / Report
Check locallyOnly where the soils, a slope or the building department call for borings.
Wetlands Delineation
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Flood / Floodplain Study
Check locallyLikely needed for a project like this. Check for wetlands, floodplain or other environmental conditions.
Stormwater / Drainage Study
Check locallySome towns ask for a drainage plan for a new building.
Land Use & Entitlements
Variance (Zoning Board of Appeals)
Check locallyThe board holds a hearing within 65 days and decides within 100 days of filing, or the variance is granted.
- Agency
- Zoning Board of Appeals
- Clock
- Set by law
- Source
- malegislature.gov
Local Historic District Certificate
Check locallyOnly in a historic district, where the commission reviews new buildings.
- Agency
- Local historic district commission
- State rule
- Only in a local historic district. The commission decides within 60 days of filing or a certificate issues.
- Clock
- Set by law
- Source
- malegislature.gov
Zoning Permit
RequiredThe zoning office confirms the new building meets the setbacks, height and lot coverage. In Massachusetts the building inspector enforces zoning and must withhold a building permit that would violate it.
- Agency
- Building commissioner or inspector of buildings
- Source
- malegislature.gov
HOA or Architectural Review Approval
Check locallyAn HOA may need to approve the house design before it is built.
Design & Permit Documents
Civil Design Package
Check locallyMany towns ask for a lot grading and utility plan for a new building.
Architectural Design Package
RequiredThe building drawings, from design through the permit set.
Structural Design Package
LikelyThe structural drawings the building permit is reviewed on.
Fire Protection Design Package
Check locallyOnly where the building code or the town requires sprinklers.
Foundation Design
LikelyThe foundation design for the new building.
Energy Code Package (Base, Stretch or Specialized Code)
RequiredCheck which energy code the town adopted. Stretch and Specialized Code towns need a HERS rating or Passive House for new homes.
- Agency
- Local building official
- Source
- mass.gov
Permit Drawing Set
RequiredThe signed and sealed drawing sets the building department reviews.
Issued-for-Construction Drawing Set
LikelyThe final drawings the trades build from, with the permit comments included.
Environmental & Site Authorizations
Soil / Erosion Control Approval
Check locallyShovelCue has no Massachusetts record for this line yet, so check who handles it for this site.
Utilities & Infrastructure
Water Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Sewer Service Approval
Check locallyLikely needed for a project like this, since new buildings need new utility service.
Electric Service Approval
Check locallyAsk the electric utility early. It answers a capacity request within three weeks, then you file the work request for service.
- Agency
- Eversource, National Grid, Unitil or the municipal light plant
- Source
- mass.gov
Road Opening Permit
LikelyA new driveway or utility connection in the street needs a road opening permit.
Permits & Construction Authorizations
Demolition Permit
Check locallyUsual when an existing structure is demolished.
Building Permit
RequiredThe building official must issue or deny the permit in writing within 30 days of filing under the state building code.
- Agency
- Building commissioner or inspector of buildings
- Clock
- Set by law
- Source
- mass.gov
Plumbing Permit
RequiredOnly a licensed plumber can take out the permit, before work starts. The inspector acts on the application within two working days.
- Agency
- Local plumbing and gas inspector
- Source
- mass.gov
Electrical Permit
RequiredThe electrician gives the inspector of wires the permit notice before starting or within five days after starting.
- Agency
- Local inspector of wires
- Source
- malegislature.gov
Mechanical / HVAC Permit
RequiredThe heating and cooling permit, reviewed with the building permit.
Fire Protection Permit
Check locallyOnly where the building code or the town requires sprinklers.
Retaining Wall Permit
Check locallyOnly if the scope includes it.
Temporary Power Permit
LikelyLets the utility connect temporary power for construction.
Board of Health Approval (Title 5 Septic Permit)
Check locallyOnly with a well or septic system, or food service.
- Agency
- Local board of health
- State rule
- A site on a septic system needs a disposal system construction permit from the board of health before any system work.
- Source
- mass.gov
Certificate of Occupancy and Use
RequiredEvery occupiable building needs it before use.
- Agency
- Building commissioner or inspector of buildings
- State rule
- The building commissioner issues the certificate within 10 days once the final inspection finds no violations.
- Clock
- Set by law
- Source
- mass.gov
Construction Readiness
Construction Entrance Installed
LikelyA stabilized entrance so trucks do not track soil onto the road.
Erosion / Sediment Controls Installed
LikelySilt fence and controls in place before digging, as the erosion control plan shows.
Dig Safe Notice (811)
LikelyMark the dig area in white and notify Dig Safe at least 72 business hours before digging. A ticket lasts 30 days.
- Agency
- Dig Safe System (811)
- Clock
- Set by law
- Source
- mass.gov
Survey Control Established
LikelyThe surveyor sets control points so the building goes in the right place.
Required Site Signage / Postings Complete
LikelyThe permit placard and the labor postings on site.
Site Ready to Mobilize
LikelyThe milestone for your target construction start.
Sources
- malegislature.govVariance (Zoning Board of Appeals)
- malegislature.govLocal Historic District Certificate
- malegislature.govZoning Permit
- mass.govEnergy Code Package (Base, Stretch or Specialized Code)
- mass.govElectric Service Approval
- mass.govBuilding Permit
- mass.govPlumbing Permit
- malegislature.govElectrical Permit
- mass.govBoard of Health Approval (Title 5 Septic Permit)
- mass.govDig Safe Notice (811)
Items with no source link come from the national list and are decided by the town or the site. Ask the local office.
Other project types in Massachusetts
This is general information from public sources. It is not legal advice. Confirm every item with your town and the agencies named before you rely on it.